
Estimating activity duration means predicting the amount of time required to complete a specific task or activity in a project.
Estimating activity duration means predicting the amount of time required to complete a specific task or activity in a project.
π It answers the question: βHow long will this task take?β
π Example: Senior developer estimates coding time
π Example: Previous login system took 3 days β similar estimate used
π Formula:
Duration = Work / Productivity Rate
π Example: 100 pages Γ· 10 pages/day = 10 days
Uses three estimates:
π Formula (PERT):
Expected Time (TE) = (O + 4M + P) / 6
π Example:
TE = (2 + 4Γ4 + 8) / 6 = (2 + 16 + 8)/6 = 26/6 β 4.33 days
π More accurate but time-consuming
π Avoid vague terms like βsoonβ or βquicklyβ
π Activity duration estimation is often shown in:
Task: Develop login feature
| Estimate Type | Time |
|---|---|
| Optimistic | 2 days |
| Most Likely | 3 days |
| Pessimistic | 6 days |
π Using PERT:
TE = (2 + 4Γ3 + 6)/6 = (2 + 12 + 6)/6 = 20/6 β 3.33 days
Duration β Effort π (Effort = total work, Duration = calendar time)
Use PERT formula for accuracy
Consider risks and uncertainties
Always base estimates on data or experience
β Ignoring risks β Over-optimistic estimates β Not considering dependencies β Lack of historical data
Estimating activity duration = predicting time required for tasks
Uses techniques like:
Accurate estimation is key for successful scheduling
Estimating activity duration is the process of predicting the time required to complete a project task. It uses techniques such as expert judgment and PERT, and is essential for creating an effective project schedule.
Open this section to view and download past papers
Click on Show Past Papers to load available exam papers.